The state of play with the St James Park redevelopment on Wednesday, June 21.

Changing rooms:

A lot of work has now been conducted on the draining system. The away changing room drainage has now been fully laid, with the remaining changing rooms drainage in the processof being finished.

The weatherproofing of the IP Office Main Stand has now been completed, and the seats have started to be put back in place.

Away end:

The original terrace has been removed from the away end.

The perimiter wall has been lowered to allow for further development.

Big Bank:

The drainage is currently being laid for the new toilet facilities at the Big Bank.

Thanks to the amazing work of the groundsmen, and having the protective hoarding in place in the away end, the St James Park pitch is looking fantastic in the sun.